Gantt chart

Gantt Chart will provide you, a bird’s eye view of the tasks in you project. Here you can schedule your task and plan it easily.
Output Time Gantt Chart
Gantt chart provides you the pictorial view on Tasks.
Each Task is listed within its time frame. You can edit the duration of the task by dragging between the date frame.
The color of the task bar represents the Task status, which will change on changing the status. Parent Tasks are represented by grey bar.
Current date is indicated by a blue dotted line.
Project Milestones are represented in Black Diamond shape. If the targeted date of milestone exceeds, it will be indicated in Red Diamond shape.
You can zoom in and zoom out the gantt chart with Weekly, Monthly, Half yearly views.

Assigning Task Dependencies

Predecessor helps you to indicate task dependencies in which activities need to be performed.

Predecessor Abbreviation Representation Explanation
Finish to Start FS OutputTime-Task-FS- Predecessor must finish before Successor can start.(default)
Start to Start SS OutputTime-Task-SS Predecessor must start before Successor can start.
Finish to Finish FF OutputTime-Task-FF Predecessor must finish before Successor can finish.
Start to Finish SF OutputTime-Task-SF Predecessor must start before Successor can finish.

Predecessors dependency types

Parent Combination Explanation
FS 1FS Task 1 must be finished to start the Successor task.
FS 2FS+3 Successor task can start after 3 days from completion of Task 2.
FS 2FS-5 Successor can start before 5 days to the completion of Task 2.
SS 1SS Task 1 must be started to start the Successor task.
SS 4SS+6 Task 4 should start 6 days before commencement of Successor.
SS 4SS-2 Task 4 should start after 2 days from the commencement of successor.
FF 1FF Task 1 must be finished to finish its Successor task.
FF 5FF+3 Task 5 should finish before 3 days to the completion of its succesor.
FF 5FF-1 Task 5 should finish 3 days after the completion of its successor.
SF 1SF Task 1 must be started to finish its Successor task.
SF 3SF+2 Task 3 row task can start before 2 days to the completion of its successor.
SF 3SF-3 Task 3 can start after 3 days from the completion of its successor.